Melton Common Wind Cluster (5 MW)

Melton Common Wind Cluster is a 5 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2017; the record was last updated on 8 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
operationalstatus in REPD
8 September 2023record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
14 June 2013Application submitted
19 December 2013Planning permission granted
1 March 2017Operational

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
8 September 2023
Operator or applicant
Seneca Global Energy
Planning authority
East Riding of Yorkshire
Planning application reference
13/01806/STPLFE
Turbines
2
Turbine height
119 m
Address (REPD)
Land South West Of Melton Waste Park Gibson Lane South Melton
Council area (by location)
East Riding of Yorkshire
Time to decision
27 weeks
REPD reference
3645

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Melton Waste Parkwind farm5operational0.5
Humberfield Recycling Centrebattery storage30approved, not built5.2
Carr Lane Solar Farmsolar farm9approved, not built6.8
Bagletts Wind Farmwind farm6.9application withdrawn6.9
Winterton Landfill Site - Ground Mounted Solar PV Arrayssolar farm5under construction7.5
Ironstone Quarry Wind Farmwind farm7.5refused7.8
Cottingham Solar Farmsolar farm5operational8.5
Saxby Wold Wind Farmwind farm36refused on appeal9.2
Wren Kitchens & Bedrooms, Parrott Streetrooftop solar6.6under construction9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7144, -0.5389).