Sancton Hill (10 MW wind farm)

Sancton Hill is a 10 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 June 2012; the record was last updated on 18 December 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
18 December 2013record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
17 May 2010Application submitted
10 February 2011Planning permission granted
1 November 2011Construction started
12 June 2012Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
18 December 2013
Operator or applicant
REG Windpower (previously Cornwall Light and Power)
Planning authority
East Riding of Yorkshire
Planning application reference
10/02080/STPLFE
Turbines
5
Address (REPD)
nr Market Weighton, Sancton, York,
Council area (by location)
East Riding of Yorkshire
Time to decision
38 weeks
REPD reference
3735

Earlier applications for this site

ApplicationMWSubmittedOutcome
Sancton Hill 08/05723/STPFE1012 December 2008refused 19 March 2009

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sober Hill Wind Farmwind farm15operational1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8451, -0.6099).