Sober Hill Wind Farm (15 MW)

Sober Hill Wind Farm is a 15 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2013; the record was last updated on 20 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
20 August 2014record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
3 October 2008Application submitted
3 April 2009Refused by the planning authority
19 March 2010Planning permission granted
19 March 2010Appeal allowed
1 March 2012Construction started
1 September 2013Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
20 August 2014
Operator or applicant
West Coast Energy
Planning authority
East Riding of Yorkshire
Planning application reference
08/04816/STPLFE
Turbines
6
Address (REPD)
Land North Of Sober Hill Farm Stoneknowle Hill North Newbald
Council area (by location)
East Riding of Yorkshire
Time to decision
76 weeks
REPD reference
4327

Earlier applications for this site

ApplicationMWSubmittedOutcome
Sober Hill Wind Farm1.51 September 1995refused 14 December 1995

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sancton Hillwind farm10operational1.4
Bagletts Wind Farmwind farm6.9application withdrawn9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8349, -0.5967).