Lissett Airfield Wind Farm (30 MW)
Lissett Airfield Wind Farm is a 30 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 February 2009; the record was last updated on 9 June 2010.
30 MWwind farm
operationalstatus in REPD
9 June 2010record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 10 July 2006 | Application submitted |
| 22 February 2007 | Planning permission granted |
| 20 February 2009 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 30 MW
- Status (REPD)
- operational
- Record last updated
- 9 June 2010
- Operator or applicant
- Novera Energy
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 06/05618/STPLFE
- Turbines
- 12
- Address (REPD)
- 1.5km west of Lisset, East Yorkshire
- Council area (by location)
- East Riding of Yorkshire
- Time to decision
- 32 weeks
- REPD reference
- 3539
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Lissett Airfield Wind Farm Extension | wind farm | 12.5 | appeal withdrawn | 0.9 |
| Land South Of Demming Farm | wind farm | 8 | refused | 3.6 |
| Fraisthorpe Wind Farm | wind farm | 29.7 | operational | 5.9 |
| Thornholme Wind Farm | wind farm | 12 | refused on appeal | 7.0 |
| Bonwick | wind farm | 17 | refused | 7.1 |
| Old Chalk Pit, West Back Side - Three Oaks Renewable Park | solar farm | 39 | approved, not built | 7.2 |
| Carnaby | wind farm | 6 | approved, not built | 7.7 |
| Back Lane, Skerne Solar Farm & Battery Storage | solar farm | 45 | approved, not built | 8.2 |
| Rotsea Wind Farm | wind farm | 6.9 | refused | 9.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0071, -0.2885).