Old Chalk Pit, West Back Side - Three Oaks Renewable Park (39 MW solar farm)

Old Chalk Pit, West Back Side - Three Oaks Renewable Park is a 39 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 March 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
25 October 2022Application submitted
21 March 2024Planning permission granted
21 March 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
39 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Ridge Clean Energy Limited
Planning authority
East Riding of Yorkshire
Planning application reference
22/02777/STPLF
Site area
68.6 ha
Address (REPD)
W/O Old Chalk Pit, West Back Side, Haisthorpe, Driffield
Council area (by location)
East Riding of Yorkshire
Time to decision
73 weeks
Contracts for Difference
AR7a
REPD reference
12525

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Thornholme Wind Farmwind farm12refused on appeal1.1
Carnabywind farm6approved, not built2.8
Land South Of Demming Farmwind farm8refused4.5
Fraisthorpe Wind Farmwind farm29.7operational4.7
Lissett Airfield Wind Farmwind farm30operational7.2
Lissett Airfield Wind Farm Extensionwind farm12.5appeal withdrawn8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.072, -0.2898).