Lissett Airfield Wind Farm Extension (12.5 MW)

Lissett Airfield Wind Farm Extension is a 12.5 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 4 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWwind farm
appeal withdrawnstatus in REPD
4 January 2016record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
30 October 2013Application submitted
6 August 2015Refused by the planning authority
20 October 2015Appeal lodged
22 December 2015Appeal withdrawn

Project details

Technology
wind farm
Capacity
12.5 MW
Status (REPD)
appeal withdrawn
Record last updated
4 January 2016
Operator or applicant
Energiekontor UK
Planning authority
East Riding of Yorkshire
Planning application reference
13/03625/STPLFE
Appeal reference
APP/E2001/W/15/3134552
Turbines
5
Address (REPD)
North Pasture Farm Out Gates Gembling East Riding Of Yorkshire YO25 8HS
Council area (by location)
East Riding of Yorkshire
Time to decision
92 weeks
REPD reference
4298

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lissett Airfield Wind Farmwind farm30operational0.9
Land South Of Demming Farmwind farm8refused4.4
Bonwickwind farm17refused6.4
Fraisthorpe Wind Farmwind farm29.7operational6.7
Back Lane, Skerne Solar Farm & Battery Storagesolar farm45approved, not built7.9
Thornholme Wind Farmwind farm12refused on appeal7.9
Old Chalk Pit, West Back Side - Three Oaks Renewable Parksolar farm39approved, not built8.1
Carnabywind farm6approved, not built8.6
Rotsea Wind Farmwind farm6.9refused8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9987, -0.2898).