Land South Of Demming Farm (8 MW wind farm)

Land South Of Demming Farm is an 8 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 27 January 2014; the record was last updated on 4 August 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
refusedstatus in REPD
4 August 2014record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
7 March 2013Application submitted
27 January 2014Refused by the planning authority

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
refused
Record last updated
4 August 2014
Operator or applicant
Airvolution Energy
Planning authority
East Riding of Yorkshire
Planning application reference
13/00316/STPLFE
Turbines
4
Address (REPD)
Demming Fraisthorpe East Riding Of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
47 weeks
REPD reference
4259

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fraisthorpe Wind Farmwind farm29.7operational2.5
Lissett Airfield Wind Farmwind farm30operational3.6
Carnabywind farm6approved, not built4.2
Lissett Airfield Wind Farm Extensionwind farm12.5appeal withdrawn4.4
Old Chalk Pit, West Back Side - Three Oaks Renewable Parksolar farm39approved, not built4.5
Thornholme Wind Farmwind farm12refused on appeal4.8
Bonwickwind farm17refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0348, -0.2614).