Fraisthorpe Wind Farm (29.7 MW)

Fraisthorpe Wind Farm is a 29.7 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 June 2016; the record was last updated on 25 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.7 MWwind farm
operationalstatus in REPD
25 October 2016record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
10 February 2012Application submitted
31 May 2012Refused by the planning authority
22 January 2013Planning permission granted
22 January 2013Appeal allowed
15 April 2015Construction started
15 June 2016Operational

Project details

Technology
wind farm
Capacity
29.7 MW
Status (REPD)
operational
Record last updated
25 October 2016
Operator or applicant
Octopus Investments
Planning authority
East Riding of Yorkshire
Planning application reference
12/00640/STPLFE
Appeal reference
12/00066/NONDET
Turbines
9
Address (REPD)
Land North East Of Manor Farm, Main Street, Fraisthorpe, East Riding Of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
50 weeks
REPD reference
4647

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land South Of Demming Farmwind farm8refused2.5
Carnabywind farm6approved, not built2.8
Old Chalk Pit, West Back Side - Three Oaks Renewable Parksolar farm39approved, not built4.7
Thornholme Wind Farmwind farm12refused on appeal5.5
Lissett Airfield Wind Farmwind farm30operational5.9
Lissett Airfield Wind Farm Extensionwind farm12.5appeal withdrawn6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0479, -0.2307).