Thornholme Wind Farm (12 MW)
Thornholme Wind Farm is a 12 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 21 May 2014; the record was last updated on 6 June 2014.
12 MWwind farm
refused on appealstatus in REPD
6 June 2014record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 7 September 2011 | Application submitted |
| 19 December 2012 | Refused by the planning authority |
| 21 May 2014 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 6 June 2014
- Operator or applicant
- Wind Prospect Developments
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 11/03999/STPLFE
- Appeal reference
- 13/00002/REFUSE
- Turbines
- 6
- Address (REPD)
- Thornholme Fields, Rudston Road, Burton Agnes, East Riding Of Yorkshire
- Council area (by location)
- East Riding of Yorkshire
- Time to decision
- 67 weeks
- REPD reference
- 3823
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Old Chalk Pit, West Back Side - Three Oaks Renewable Park | solar farm | 39 | approved, not built | 1.1 |
| Carnaby | wind farm | 6 | approved, not built | 3.9 |
| Land South Of Demming Farm | wind farm | 8 | refused | 4.8 |
| Fraisthorpe Wind Farm | wind farm | 29.7 | operational | 5.5 |
| Lissett Airfield Wind Farm | wind farm | 30 | operational | 7.0 |
| Lissett Airfield Wind Farm Extension | wind farm | 12.5 | appeal withdrawn | 7.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0694, -0.3062).