Solar, wind and battery projects near Bridlington (YO15)
16 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO15 (East Riding of Yorkshire): 2 are waiting for a planning decision, 10 approved but not yet running, 2 operational. The largest live scheme is Old Chalk Pit, West Back Side - Three Oaks Renewable Park (39 MW solar farm, approved on 21 March 2024, not yet built), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of YO15
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Carnabywind farm | wind farm | 6 | approved, not built may be out of dateupdated Jan 2020 | Nov 2010 | granted Feb 2012 | Jan 2020 | East Riding of Yorkshire | 5.2 |
| Fraisthorpe Wind Farmwind farm | wind farm | 29.7 | operationalupdated Oct 2016 | Feb 2012 | granted Jan 2013 | Oct 2016 | East Riding of Yorkshire | 6.2 |
| Old Chalk Pit, West Back Side - Three Oaks Renewable Parksolar farm | solar farm | 39 | approved, not builtupdated Feb 2026 | Oct 2022 | granted Mar 2024 | Feb 2026 | East Riding of Yorkshire | 7.7 |
| Land South Of Demming Farmwind farm | wind farm | 8 | refusedupdated Aug 2014 | Mar 2013 | refused Jan 2014 | Aug 2014 | East Riding of Yorkshire | 8.6 |
| Thornholme Wind Farmwind farm | wind farm | 12 | refused on appealupdated Jun 2014 | Sep 2011 | refused Dec 2012 | Jun 2014 | East Riding of Yorkshire | 8.8 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bessingby Roadsolar farm | solar farm | 0.4 | application submitted may be out of dateupdated May 2022 | Apr 2022 | — | May 2022 | East Riding of Yorkshire | 2.6 |
| Bessingby Roadrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated May 2022 | Apr 2022 | — | May 2022 | East Riding of Yorkshire | 2.6 |
| Bridlington And District Hospital, Bessingby Road Battery Unitbattery storage | battery storage | 0.4 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | East Riding of Yorkshire | 2.6 |
| Bridlington Waste Water Treatment Workssolar farm | solar farm | — | approved, not builtupdated Sep 2023 | Jun 2023 | granted Aug 2023 | Sep 2023 | East Riding of Yorkshire | 3.8 |
| South Shore Holiday Villagesolar farm | solar farm | 0.4 | operationalupdated Mar 2023 | Jun 2019 | granted Dec 2020 | Mar 2023 | East Riding of Yorkshire | 4.4 |
| Thornwick Bay Holiday Village, North Marine Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | East Riding of Yorkshire | 5.3 |
| Country Style Foods, Carnaby Industrial Estaterooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | East Riding of Yorkshire | 6.3 |
| B W Industries Limited, Carnaby Industrial Estaterooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2025 | Sep 2024 | granted Nov 2024 | Jan 2025 | East Riding of Yorkshire | 6.4 |
| Ab Graphic International, Carnaby Industrial Estaterooftop solar | rooftop solar | — | approved, not builtupdated Apr 2023 | Dec 2022 | granted Jan 2023 | Apr 2023 | East Riding of Yorkshire | 6.5 |
| Old Chalk Pit, West Back Side - Three Oaks Renewable Parkbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Oct 2022 | granted Mar 2024 | Feb 2026 | East Riding of Yorkshire | 7.7 |
| Reighton Sands Holiday Village, Sands Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 | North Yorkshire | 9.4 |
Distance from the average position of the YO15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 1 | 2 | 1 | 0 | 39.4 |
| Rooftop solar | 6 | 1 | 5 | 0 | 0 | 1.4 |
| Wind farm | 4 | 0 | 1 | 1 | 2 | 6 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 0.4 |
MW in pipeline: pending, approved and under-construction capacity.
How East Riding of Yorkshire decides solar, wind and battery applications
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
All projects in East Riding of Yorkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near YO15, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.