Solar, wind and battery projects near Hornsea (HU18)
11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HU18 (East Riding of Yorkshire): 1 is waiting for a planning decision, 6 approved but not yet running, 2 operational. The largest live scheme is Skipsea Lane, Dunnington Wind Farm (4.2 MW wind turbine, approved on 21 October 2022, not yet built; REPD status may be out of date), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of HU18
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Withernwick extensionwind farm | wind farm | 8.2 | operationalupdated Nov 2019 | Jun 2014 | granted Dec 2016 | Nov 2019 | East Riding of Yorkshire | 5.7 |
| Bonwickwind farm | wind farm | 17 | refusedupdated Mar 2017 | Mar 2015 | refused Feb 2017 | Mar 2017 | East Riding of Yorkshire | 6.3 |
| Skipsea Lane, Dunnington Wind Farmwind turbine | wind turbine | 4.2 | approved, not built may be out of dateupdated Mar 2022 | Mar 2022 | granted Oct 2022 | Mar 2022 | East Riding of Yorkshire | 6.8 |
| Withernwickwind farm | wind farm | 18 | operationalupdated Jun 2013 | Apr 2008 | granted Sep 2008 | Jun 2013 | East Riding of Yorkshire | 7.1 |
| Withernwick (withdrawn)wind farm | wind farm | 25 | application withdrawnupdated Jun 2010 | Apr 2007 | — | Jun 2010 | East Riding of Yorkshire | 7.2 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Far Grange Caravan Park, Hornsea Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Mar 2023 | granted Apr 2023 | Jul 2023 | East Riding of Yorkshire | 5.8 |
| Southfield House Farm, Hornsea Roadwind turbine | wind turbine | 0.2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | East Riding of Yorkshire | 6.0 |
| Cowden Magna Farm, Cowdenwind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Jan 2026 | Jan 2026 | East Riding of Yorkshire | 6.1 |
| Robinson Contract Services, Catfoss Industrial Estatesolar farm | solar farm | 1 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 | East Riding of Yorkshire | 7.1 |
| Modular & Portable Buildings Hire Limited, Brandesburtonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | East Riding of Yorkshire | 7.3 |
| Rasher House, Catfoss Lanesolar farm | solar farm | 0.4 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 | East Riding of Yorkshire | 7.3 |
Distance from the average position of the HU18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 0 | 2 | 0 | 0 | 1.4 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.6 |
| Wind farm | 4 | 0 | 0 | 2 | 1 | 0 |
| Wind turbine | 3 | 1 | 2 | 0 | 0 | 4.7 |
MW in pipeline: pending, approved and under-construction capacity.
How East Riding of Yorkshire decides solar, wind and battery applications
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
All projects in East Riding of Yorkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HU18, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.