Withernwick extension (8.2 MW wind farm)
Withernwick extension is an 8.2 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2019; the record was last updated on 19 November 2019.
8.2 MWwind farm
operationalstatus in REPD
19 November 2019record last updated
East Riding of Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 June 2014 | Application submitted |
| 10 June 2015 | Refused by the planning authority |
| 15 October 2015 | Appeal lodged |
| 19 December 2016 | Planning permission granted |
| 19 December 2016 | Appeal allowed |
| 15 September 2018 | Construction started |
| 1 August 2019 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 8.2 MW
- Status (REPD)
- operational
- Record last updated
- 19 November 2019
- Operator or applicant
- Energiekontor UK
- Planning authority
- East Riding of Yorkshire
- Planning application reference
- 14/01919/STPLFE
- Appeal reference
- APP/E2001/W/15/3133812
- Turbines
- 4
- Address (REPD)
- Land North And North East Homer House Aldbrough Road Withernwick East Riding Of Yorkshire
- Council area (by location)
- East Riding of Yorkshire
- Time to decision
- 130 weeks
- REPD reference
- 4432
Who decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Withernwick (withdrawn) | wind farm | 25 | application withdrawn | 1.5 |
| Withernwick | wind farm | 18 | operational | 1.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.859, -0.1656).