Energy Projects Near You

Withernwick extension (8.2 MW wind farm)

Withernwick extension is an 8.2 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2019; the record was last updated on 19 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWwind farm
operationalstatus in REPD
19 November 2019record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
24 June 2014Application submitted
10 June 2015Refused by the planning authority
15 October 2015Appeal lodged
19 December 2016Planning permission granted
19 December 2016Appeal allowed
15 September 2018Construction started
1 August 2019Operational

Project details

Technology
wind farm
Capacity
8.2 MW
Status (REPD)
operational
Record last updated
19 November 2019
Operator or applicant
Energiekontor UK
Planning authority
East Riding of Yorkshire
Planning application reference
14/01919/STPLFE
Appeal reference
APP/E2001/W/15/3133812
Turbines
4
Address (REPD)
Land North And North East Homer House Aldbrough Road Withernwick East Riding Of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
130 weeks
REPD reference
4432

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Withernwick (withdrawn)wind farm25application withdrawn1.5
Withernwickwind farm18operational1.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.859, -0.1656).