Withernwick (withdrawn) (25 MW wind farm)

Withernwick (withdrawn) is a 25 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 17 October 2007; the record was last updated on 9 June 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWwind farm
application withdrawnstatus in REPD
9 June 2010record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
5 April 2007Application submitted
17 October 2007Application withdrawn

Project details

Technology
wind farm
Capacity
25 MW
Status (REPD)
application withdrawn
Record last updated
9 June 2010
Operator or applicant
Energiekontor UK
Planning authority
East Riding of Yorkshire
Planning application reference
07/02271/STPLFE
Turbines
11
Address (REPD)
Land South North And North East Homer House Aldbrough Road Withernwick East Riding Of Yorkshire
Council area (by location)
East Riding of Yorkshire
REPD reference
2998

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Withernwickwind farm18operational0.4
Withernwick extensionwind farm8.2operational1.5
Hull Solar Farmsolar farm25.7under construction9.4
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storage20approved, not built9.8
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farm49.9approved, not built9.8
Turf Carr Solar Farmsolar farm49.9approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8452, -0.1664).