Withernwick (18 MW wind farm)

Withernwick is an 18 MW wind farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 March 2013; the record was last updated on 3 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
operationalstatus in REPD
3 June 2013record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
4 April 2008Application submitted
2 September 2008Planning permission granted
1 April 2012Construction started
19 March 2013Operational

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
3 June 2013
Operator or applicant
Energiekontor UK
Planning authority
East Riding of Yorkshire
Planning application reference
08/01964/STPLFE
Appeal reference
08/00213/REFUSE
Turbines
9
Address (REPD)
Land North And North East Homer House Aldbrough Road Withernwick East Riding Of Yorkshire
Council area (by location)
East Riding of Yorkshire
Time to decision
22 weeks
REPD reference
3987

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Withernwick (withdrawn)wind farm25application withdrawn0.4
Withernwick extensionwind farm8.2operational1.6
Hull Solar Farmsolar farm25.7under construction9.2
Turf Carr Solar Farmsolar farm49.9approved, not built9.5
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farm49.9approved, not built9.7
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storage20approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8457, -0.1726).