Energy Projects Near You

Solar, wind and battery projects near Scarborough (YO11)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO11 (North Yorkshire): 6 approved but not yet running. The largest live scheme is Eastgate House Farm, Seamer Solar Farm (32 MW solar farm, under construction since 1 January 2024), 2.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
6approved, not running
0operational

Projects within 10 km of YO11

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Queen Margarets Industrial Estatebattery storagebattery storage18abandonedupdated Dec 2019Jul 2018—Dec 2019North Yorkshire1.1
Eastgate House Farm, Seamer Solar Farmsolar farmsolar farm32under constructionupdated Apr 2024Aug 2021granted Oct 2022Apr 2024North Yorkshire2.5
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mccain Foods GB, Havers Hill Solar Canopiessolar farmsolar farm—refusedupdated Jun 2025Apr 2025refused May 2025Jun 2025North Yorkshire2.9
William Hare, Eastfieldrooftop solarrooftop solar0.5approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025North Yorkshire3.0
Cayton Bay Holiday Park, Mill Lanerooftop solarrooftop solar0.3approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024North Yorkshire3.2
Scarborough Hospital, Woodlands Driverooftop solarrooftop solar0.5approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026North Yorkshire3.2
Magdalen Grange Farm, Carr Lanewind turbinewind turbine0.2approved, not builtupdated Apr 2026Oct 2025granted Mar 2026Apr 2026North Yorkshire6.5
Filey Waste Water Treatment Works, Carr House Farmsolar farmsolar farm0.2approved, not builtupdated Oct 2023May 2023granted Oct 2023Oct 2023North Yorkshire7.2

Distance from the average position of the YO11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3020132.2
Rooftop solar303001.2
Wind turbine101000.2
Battery storage100000

MW in pipeline: pending, approved and under-construction capacity.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.