Energy Projects Near You

Solar, wind and battery projects near Filey (YO14)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO14 (North Yorkshire): 2 are waiting for a planning decision, 10 approved but not yet running. The largest live scheme is Eastgate House Farm, Seamer Solar Farm (32 MW solar farm, under construction since 1 January 2024), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
2awaiting a decision
10approved, not running
0operational

Projects within 10 km of YO14

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Eastgate House Farm, Seamer Solar Farmsolar farmsolar farm32under constructionupdated Apr 2024Aug 2021granted Oct 2022Apr 2024North Yorkshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Haven Leisure, Primrose Avenuerooftop solarrooftop solar0.7approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023North Yorkshire1.5
Filey Waste Water Treatment Works, Carr House Farmsolar farmsolar farm0.2approved, not builtupdated Oct 2023May 2023granted Oct 2023Oct 2023North Yorkshire2.5
Magdalen Grange Farm, Carr Lanewind turbinewind turbine0.2approved, not builtupdated Apr 2026Oct 2025granted Mar 2026Apr 2026North Yorkshire3.4
Deep Sea Electronics, Bridlingtonrooftop solarrooftop solar0.4approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024North Yorkshire3.8
Reighton Sands Holiday Village, Sands Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023North Yorkshire4.6
Bartindale Road, Grindalewind turbinewind turbine0.2approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025North Yorkshire5.4
Hunmanby Grange, Cans Dale To The Grange Solar Panels & BESSrooftop solarrooftop solar0.3application submittedMay 2026——North Yorkshire5.6
Cayton Bay Holiday Park, Mill Lanerooftop solarrooftop solar0.3approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024North Yorkshire6.5
Burton Fleming Grange, Wold Newton Roadwind turbinewind turbine0.7approved, not builtupdated Sep 2023Apr 2023granted Aug 2023Sep 2023East Riding of Yorkshire7.2
North Fordon Farm, Danebury Manor Roadwind turbinewind turbine0.2application submittedMay 2026——East Riding of Yorkshire7.4
Mccain Foods GB, Havers Hill Solar Canopiessolar farmsolar farm—refusedupdated Jun 2025Apr 2025refused May 2025Jun 2025North Yorkshire7.4
William Hare, Eastfieldrooftop solarrooftop solar0.5approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025North Yorkshire8.8

Distance from the average position of the YO14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3020132.2
Rooftop solar615002.3
Wind turbine413001.4

MW in pipeline: pending, approved and under-construction capacity.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.