Energy Projects Near You

Back Lane, Skerne Solar Farm & Battery Storage (45 MW)

Back Lane, Skerne Solar Farm & Battery Storage is a 45 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 October 2020, not yet built; the record was last updated on 18 November 2022. REPD records the planning permission as expiring on 23 October 2023, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWsolar farm
approved, not builtmay be out of datestatus in REPD
18 November 2022record last updated
East Riding of Yorkshirecouncil area

REPD records the planning permission as expiring on 23 October 2023, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
10 July 2020Application submitted
23 October 2020Planning permission granted
23 October 2023Permission expired

Project details

Technology
solar farm
Capacity
45 MW
Status (REPD)
approved, not built
Record last updated
18 November 2022
Operator or applicant
BayWa r.e. UK Limited
Planning authority
East Riding of Yorkshire
Planning application reference
20/01962/STPLF
Address (REPD)
Back Lane, Skerne, Driffield
Council area (by location)
East Riding of Yorkshire
Time to decision
15 weeks
Contracts for Difference
AR4
Name in REPD
Back Lane, Skerne - Solar Farm & Battery Storage
REPD reference
12296

The scheme also includes 30 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sunderlandwick Solar Farmsolar farm49.9approved, not built1.9
Scurf Dyke Solar Farmsolar farm49.9approved, not built3.5
Rotsea Wind Farmwind farm6.9refused4.9
Lissett Airfield Wind Farm Extensionwind farm12.5appeal withdrawn7.9
Lissett Airfield Wind Farmwind farm30operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9833, -0.408).