Sunderlandwick Solar Farm (49.9 MW)

Sunderlandwick Solar Farm is a 49.9 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 April 2023, not yet built; the record was last updated on 20 February 2026. REPD records the planning permission as expiring on 21 April 2026, but the project holds a Contracts for Difference award (AR7a), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
20 February 2026record last updated
East Riding of Yorkshirecouncil area

REPD records the planning permission as expiring on 21 April 2026, but the project holds a Contracts for Difference award (AR7a), so construction may have started.

Planning timeline

DateStage
25 August 2022Application submitted
21 April 2023Planning permission granted
21 April 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Elgin Energy EsCo Limited
Planning authority
East Riding of Yorkshire
Planning application reference
22/02460/STPLF
Site area
76.4 ha
Address (REPD)
SE/O Poundsworth Beverley Road Driffield
Council area (by location)
East Riding of Yorkshire
Time to decision
34 weeks
Contracts for Difference
AR7a
REPD reference
12008

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Back Lane, Skerne Solar Farm & Battery Storagesolar farm45approved, not built1.9
Scurf Dyke Solar Farmsolar farm49.9approved, not built3.9
Rotsea Wind Farmwind farm6.9refused5.8
High Wood Wind Farmwind farm25application withdrawn8.2
Lissett Airfield Wind Farm Extensionwind farm12.5appeal withdrawn9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.983, -0.4372).