Energy Projects Near You

Station Road, Carlton (99 MW battery storage)

Station Road, Carlton is a 99 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 May 2025, not yet built; the record was last updated on 2 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
approved, not builtstatus in REPD
2 June 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
9 October 2024Application submitted
14 May 2025Planning permission granted
14 May 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
approved, not built
Record last updated
2 June 2025
Operator or applicant
Root Power (North) Limited
Planning authority
North Yorkshire
Planning application reference
ZG2024/1052/FULM
Address (REPD)
E/O Station Road, Carlton, Goole
Council area (by location)
North Yorkshire
Time to decision
31 weeks
Name in REPD
Station Road, Carlton - Battery Energy Storage System
REPD reference
17577

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carlton Solar Farmsolar farm50approved, not built2.4
Camblesforth Solar Farmsolar farm49.9approved, not built2.5
Drax Re-Powerbattery storage200approved, not built2.6
Hales Lanebattery storage100approved, not built2.6
Lakeside Energy Storage Facilitybattery storage99.9approved, not built2.9
Helios Renewable Energy Projectsolar farm190approved, not built3.7
Rusholme Wind Farmwind farm24operational5.0
Aire & Calder Wind Farmwind farm45application withdrawn5.1
Land at Pollington Airfieldsolar farm5operational5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7136, -1.0191).