Osgodby Grange, Osgodby Solar Energy (49.9 MW)
Osgodby Grange, Osgodby Solar Energy is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 July 2022, not yet built; the record was last updated on 31 March 2026. REPD also records that the planning permission expired on 15 July 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.
REPD also records that the planning permission expired on 15 July 2025, so the project may not go ahead in this form.
Planning timeline
| Date | Stage |
|---|---|
| 6 September 2021 | Application submitted |
| 15 July 2022 | Planning permission granted |
| 15 July 2025 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 49.9 MW
- Status (REPD)
- approved, not built
- Record last updated
- 31 March 2026
- Operator or applicant
- Enray Power Limited
- Planning authority
- North Yorkshire
- Planning application reference
- 2021/0978/FULM
- Site area
- 77.2 ha
- Address (REPD)
- Osgodby Grange, South Duffield Road, Osgodby, Selby
- Council area (by location)
- North Yorkshire
- Time to decision
- 45 weeks
- Name in REPD
- Osgodby Grange, Osgodby - Solar Energy
- REPD reference
- 9075
Who decides
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Hull Road, Lund | battery storage | 40 | approved, not built | 1.9 |
| Cleek Hall | wind farm | 15 | abandoned | 2.2 |
| Newlands Farm, Turnham Lane | solar farm | 49.9 | application submitted | 2.4 |
| Barlow Road, Barlow Road | battery storage | 80 | application withdrawn | 3.9 |
| Redmoor Farm | solar farm | 25.5 | permission expired | 5.4 |
| Camblesforth Solar Farm | solar farm | 49.9 | approved, not built | 6.8 |
| Drax Re-Power | battery storage | 200 | approved, not built | 7.3 |
| Lakeside Energy Storage Facility | battery storage | 99.9 | approved, not built | 7.3 |
| Hales Lane | battery storage | 100 | approved, not built | 8.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.797, -1.0144).