Energy Projects Near You

Osgodby Grange, Osgodby Solar Energy (49.9 MW)

Osgodby Grange, Osgodby Solar Energy is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 July 2022, not yet built; the record was last updated on 31 March 2026. REPD also records that the planning permission expired on 15 July 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
31 March 2026record last updated
North Yorkshirecouncil area

REPD also records that the planning permission expired on 15 July 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
6 September 2021Application submitted
15 July 2022Planning permission granted
15 July 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
Enray Power Limited
Planning authority
North Yorkshire
Planning application reference
2021/0978/FULM
Site area
77.2 ha
Address (REPD)
Osgodby Grange, South Duffield Road, Osgodby, Selby
Council area (by location)
North Yorkshire
Time to decision
45 weeks
Name in REPD
Osgodby Grange, Osgodby - Solar Energy
REPD reference
9075

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hull Road, Lundbattery storage40approved, not built1.9
Cleek Hallwind farm15abandoned2.2
Newlands Farm, Turnham Lanesolar farm49.9application submitted2.4
Barlow Road, Barlow Roadbattery storage80application withdrawn3.9
Redmoor Farmsolar farm25.5permission expired5.4
Camblesforth Solar Farmsolar farm49.9approved, not built6.8
Drax Re-Powerbattery storage200approved, not built7.3
Lakeside Energy Storage Facilitybattery storage99.9approved, not built7.3
Hales Lanebattery storage100approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.797, -1.0144).