Hull Road, Lund (40 MW battery storage)

Hull Road, Lund is a 40 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 January 2025, not yet built; the record was last updated on 31 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
31 January 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
23 July 2024Application submitted
21 January 2025Planning permission granted
21 January 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
31 January 2025
Operator or applicant
Ylem Energy Limited
Planning authority
North Yorkshire
Planning application reference
ZG2024/0630/FUL
Address (REPD)
West of Hulll Road, Lund, Selby
Council area (by location)
North Yorkshire
Time to decision
26 weeks
Name in REPD
Hull Road, Lund - Battery Energy Storage System
REPD reference
16921

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cleek Hallwind farm15abandoned0.7
Newlands Farm, Turnham Lanesolar farm49.9application submitted1.9
Osgodby Grange, Osgodby Solar Energysolar farm49.9approved, not built1.9
Barlow Road, Barlow Roadbattery storage80application withdrawn3.8
Camblesforth Solar Farmsolar farm49.9approved, not built5.2
Lakeside Energy Storage Facilitybattery storage99.9approved, not built5.5
Drax Re-Powerbattery storage200approved, not built5.5
Hales Lanebattery storage100approved, not built6.3
Carlton Solar Farmsolar farm50approved, not built6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7813, -1.0021).