Scalm Park / Bishopwood (17.5 MW wind farm)

Scalm Park / Bishopwood is a 17.5 MW wind farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 30 August 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.5 MWwind farm
appeal withdrawnstatus in REPD
30 August 2018record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
1 July 2009Application submitted
14 January 2013Refused by the planning authority
22 October 2013Appeal lodged
6 November 2015Appeal withdrawn

Project details

Technology
wind farm
Capacity
17.5 MW
Status (REPD)
appeal withdrawn
Record last updated
30 August 2018
Operator or applicant
ProWind GMBH
Planning authority
North Yorkshire
Planning application reference
09/0464/FUL
Appeal reference
APP/N2739/A/13/2201308
Turbines
7
Address (REPD)
Wistow Common, Selby, North Yorks
Council area (by location)
North Yorkshire
Time to decision
185 weeks
REPD reference
3679

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Scalm Park, Wistow Solar Farm & Battery Energy Storagesolar farm49.9approved, not built<0.1
Broad Lane, Cawood Solar Farm & Battery Storagesolar farm49.9application submitted4.4
Solar Farm at Woodcock Solar Farmsolar farm18.5refused4.6
Land at Ash Row Farmsolar farm5operational4.9
Kingspan Insulation Solar Installationrooftop solar5operational5.5
Barlow Road, Barlow Roadbattery storage80application withdrawn5.9
Hillam Grange, Austfield Lane Solar Farmsolar farm49.9approved, not built6.5
Solar Farm at Light Valley Solar Sitessolar farm500application submitted6.5
Wood Lanewind farm32.2application withdrawn6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7909, -1.1429).