Energy Projects Near You

Scalm Park, Wistow Solar Farm & Battery Energy Storage (49.9 MW)

Scalm Park, Wistow Solar Farm & Battery Energy Storage is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 September 2025, not yet built; the record was last updated on 30 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
30 September 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
19 November 2024Application submitted
11 September 2025Planning permission granted
11 September 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
30 September 2025
Operator or applicant
Grenergy
Planning authority
North Yorkshire
Planning application reference
ZG2024/1129/FULM
Site area
94.0 ha
Address (REPD)
Scalm Park Wistow
Council area (by location)
North Yorkshire
Time to decision
42 weeks
Name in REPD
Scalm Park, Wistow - Solar Farm & Battery Energy Storage
REPD reference
16647

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Scalm Park / Bishopwoodwind farm17.5appeal withdrawn<0.1
Broad Lane, Cawood Solar Farm & Battery Storagesolar farm49.9application submitted4.4
Solar Farm at Woodcock Solar Farmsolar farm18.5refused4.6
Land at Ash Row Farmsolar farm5operational4.9
Kingspan Insulation Solar Installationrooftop solar5operational5.5
Barlow Road, Barlow Roadbattery storage80application withdrawn5.9
Hillam Grange, Austfield Lane Solar Farmsolar farm49.9approved, not built6.5
Solar Farm at Light Valley Solar Sitessolar farm500application submitted6.5
Wood Lanewind farm32.2application withdrawn6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7909, -1.1429).