Kingspan Insulation Solar Installation (5 MW)

Kingspan Insulation Solar Installation is a 5 MW rooftop solar project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 1 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWrooftop solar
operationalstatus in REPD
1 June 2017record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
11 December 2013Application submitted
12 March 2014Planning permission granted
13 March 2014Construction started
31 March 2014Operational

Project details

Technology
rooftop solar
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 June 2017
Operator or applicant
Kingspan Insulation/ Eneco
Planning authority
North Yorkshire
Planning application reference
2013/1173/FUL
Address (REPD)
Enterprise Way, Sherburn In Elmet, North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
13 weeks
REPD reference
1294

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Ash Row Farmsolar farm5operational0.6
Solar Farm at Woodcock Solar Farmsolar farm18.5refused2.2
Solar Farm at Light Valley Solar Sitessolar farm500application submitted3.8
Hillam Grange, Austfield Lane Solar Farmsolar farm49.9approved, not built4.1
Monk Fryston Battery Storagebattery storage57under construction5.1
Monk Fryston Battery Storagebattery storage320under construction5.3
Scalm Park, Wistow Solar Farm & Battery Energy Storagesolar farm49.9approved, not built5.5
Scalm Park / Bishopwoodwind farm17.5appeal withdrawn5.5
Rawfield Lanebattery storage200approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7944, -1.2259).