Energy Projects Near You

Monk Fryston Battery Storage (57 MW)

Monk Fryston Battery Storage is a 57 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 August 2023; the record was last updated on 14 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
under constructionstatus in REPD
14 October 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
19 May 2021Application submitted
7 January 2022Appeal lodged
1 August 2022Planning permission granted
1 August 2022Appeal allowed
1 August 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
under construction
Record last updated
14 October 2025
Operator or applicant
Pelagic Energy / Constantine
Planning authority
North Yorkshire
Planning application reference
2021/0633/FULM
Appeal reference
APP/N2739/W/22/3290256
Address (REPD)
Land South Of Electricity Substation Rawfield Lane, Fairburn, Selby,
Council area (by location)
North Yorkshire
Time to decision
63 weeks
REPD reference
19593

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monk Fryston Battery Storagebattery storage320under construction0.2
Rawfield Lanebattery storage200approved, not built1.3
Solar Farm at Light Valley Solar Sitessolar farm500application submitted2.6
Hillam Grange, Austfield Lane Solar Farmsolar farm49.9approved, not built2.7
Kirkhaw Lane Battery Storage Energybattery storage150operational3.8
Kirkhaw Lanebattery storage20operational4.1
Kirkhaw Lanebattery storage100abandoned4.1
Kingspan Insulation Solar Installationrooftop solar5operational5.1
Wood Lanewind farm32.2application withdrawn5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7544, -1.2651).