Energy Projects Near You

Monk Fryston Battery Storage (320 MW)

Monk Fryston Battery Storage is a 320 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 April 2024; the record was last updated on 14 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

320 MWbattery storage
under constructionstatus in REPD
14 October 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
23 June 2021Application submitted
15 December 2021Refused by the planning authority
7 June 2022Appeal lodged
1 December 2022Planning permission granted
1 December 2022Appeal allowed
1 April 2024Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
320 MW
Status (REPD)
under construction
Record last updated
14 October 2025
Operator or applicant
SSE Renewables
Planning authority
North Yorkshire
Planning application reference
2021/0789/FULM
Appeal reference
APP/N2739/W/22/3300623
Address (REPD)
Land South Of Electricity Substation Rawfield Lane, Fairburn, Selby,
Council area (by location)
North Yorkshire
Time to decision
75 weeks
REPD reference
15164

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monk Fryston Battery Storagebattery storage57under construction0.2
Rawfield Lanebattery storage200approved, not built1.1
Solar Farm at Light Valley Solar Sitessolar farm500application submitted2.7
Hillam Grange, Austfield Lane Solar Farmsolar farm49.9approved, not built2.9
Kirkhaw Lane Battery Storage Energybattery storage150operational3.7
Kirkhaw Lanebattery storage20operational4.0
Kirkhaw Lanebattery storage100abandoned4.0
Kingspan Insulation Solar Installationrooftop solar5operational5.3
Wood Lanewind farm32.2application withdrawn5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7536, -1.2676).