Solar, wind and battery projects near Castleford (WF10)
46 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WF10 (Wakefield): 8 are waiting for a planning decision, 26 approved but not yet running, 6 operational. The largest live scheme is Solar Farm at Light Valley Solar Sites (500 MW solar farm, application submitted on 9 March 2026, no decision recorded), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WF10
Projects of 1 MW and more (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Newton Lane, Ledstonbattery storage | battery storage | 25 | approved, not builtupdated Jun 2026 | Oct 2024 | granted May 2026 | Jun 2026 | Leeds | 2.7 |
| Barnsdale Roadbattery storage | battery storage | 3 | application withdrawnupdated Jun 2019 | May 2018 | — | Jun 2019 | Leeds | 3.1 |
| Barnsdale Road Solar Parkbattery storage | battery storage | 40 | application withdrawnupdated Oct 2024 | Jul 2023 | — | Oct 2024 | Leeds | 3.1 |
| Barnsdale Road Solar Parksolar farm | solar farm | 40 | under constructionupdated Aug 2025 | Dec 2020 | granted Oct 2021 | Aug 2025 | Leeds | 3.9 |
| Pontefract Wind Farmwind farm | wind farm | 12 | refused on appealupdated Dec 2010 | May 2007 | refused Feb 2008 | Dec 2010 | Wakefield | 4.6 |
| Kirkhaw Lane Battery Storage Energybattery storage | battery storage | 150 | operationalupdated Mar 2026 | Nov 2021 | granted Jun 2023 | Mar 2026 | Wakefield | 4.7 |
| Kirkhaw Lanebattery storage | battery storage | 20 | operationalupdated Jan 2022 | Jul 2017 | granted Oct 2019 | Jan 2022 | Wakefield | 4.7 |
| Kirkhaw Lanebattery storage | battery storage | 100 | abandonedupdated Jan 2025 | Feb 2024 | granted Jul 2024 | Jan 2025 | Wakefield | 4.8 |
| Siniat, Kirkhaw Lanerooftop solar | rooftop solar | 3 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Dec 2024 | Jan 2025 | Wakefield | 4.8 |
| Cooksland Farm, Old Snydale -Battery Energy Storagebattery storage | battery storage | 50 | approved, not builtupdated Mar 2026 | May 2024 | granted Nov 2025 | Mar 2026 | Wakefield | 4.8 |
| Rawfield Lanebattery storage | battery storage | 200 | approved, not builtupdated Sep 2025 | Oct 2024 | granted Aug 2025 | Sep 2025 | North Yorkshire | 5.1 |
| Phoenix Healthcare Distribution Centrebattery storage | battery storage | 3.4 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Wakefield | 5.8 |
| Phoenix Healthcare Distribution Centrerooftop solar | rooftop solar | 3.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Wakefield | 5.8 |
| Monk Fryston Battery Storagebattery storage | battery storage | 320 | under constructionupdated Oct 2025 | Jun 2021 | granted Dec 2022 | Oct 2025 | North Yorkshire | 6.2 |
| Monk Fryston Battery Storagebattery storage | battery storage | 57 | under constructionupdated Oct 2025 | May 2021 | granted Aug 2022 | Oct 2025 | North Yorkshire | 6.4 |
| Headways, Unit 3rooftop solar | rooftop solar | 1 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | Wakefield | 6.7 |
| Knottingley Asolar farm | solar farm | 5 | operationalupdated May 2016 | Aug 2014 | granted Jan 2015 | May 2016 | Wakefield | 7.3 |
| Knottingley Bsolar farm | solar farm | 2.4 | operationalupdated May 2016 | Oct 2015 | granted Jan 2016 | May 2016 | Wakefield | 7.3 |
| Darrington Quarrywind farm | wind farm | 16 | application withdrawnupdated Jun 2016 | Dec 2010 | — | Jun 2016 | Wakefield | 7.3 |
| Skelton Grange Landfill Site, Pontefract Lane Solar Farmsolar farm | solar farm | 4.4 | approved, not builtupdated Oct 2023 | Dec 2022 | granted Sep 2023 | Oct 2023 | Leeds | 8.4 |
| Leys Lanesolar farm | solar farm | 49.9 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 | North Yorkshire | 8.6 |
| Solar Farm at Light Valley Solar Sitessolar farm | solar farm | 500 | application submittedupdated Jun 2026 | Mar 2026 | — | Jun 2026 | North Yorkshire | 8.9 |
| Hillam Grange, Austfield Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jan 2026 | Dec 2023 | granted Dec 2025 | Jan 2026 | North Yorkshire | 9.0 |
| Stocking Lane Battery Energy Facilitybattery storage | battery storage | 200 | application submitted may be out of dateupdated Oct 2023 | Sep 2023 | — | Oct 2023 | North Yorkshire | 9.3 |
| Weeland Road, Kellingley Solar Farmsolar farm | solar farm | 10 | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 | North Yorkshire | 9.5 |
| Westfield Road, Carltonbattery storage | battery storage | 50 | approved, not builtupdated Jul 2025 | Nov 2023 | granted Jul 2025 | Jul 2025 | Leeds | 9.8 |
| Hook Moorwind farm | wind farm | 10.3 | operationalupdated Feb 2016 | Feb 2008 | granted Dec 2011 | Feb 2016 | Leeds | 9.8 |
| Sudforth Lane (Kellingley Solar Farm)solar farm | solar farm | 5 | operationalupdated Oct 2017 | Apr 2015 | granted Aug 2015 | Oct 2017 | North Yorkshire | 9.9 |
| Neil Fox Waybattery storage | battery storage | 99.9 | application submitted may be out of dateupdated Sep 2022 | Jul 2022 | — | Sep 2022 | Wakefield | 10.0 |
| Neil Fox Waybattery storage | battery storage | 99.9 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Wakefield | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Castleford Wastewater Treatment Works, Wheldon Roadsolar farm | solar farm | 0.3 | refusedupdated Sep 2024 | Jul 2024 | refused Aug 2024 | Sep 2024 | Wakefield | 1.6 |
| Steamboat Way, Glasshoughtonrooftop solar | rooftop solar | 0.8 | application submitted | Jun 2026 | — | — | Wakefield | 1.7 |
| Unit G1, Whistler Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2022 | May 2022 | granted Sep 2022 | Jun 2022 | Wakefield | 2.0 |
| Chep UK, Park Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jun 2023 | Jul 2023 | Wakefield | 3.1 |
| Sharpsmart, Loscoe Closerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Wakefield | 3.7 |
| Ferrybridge 2, Fryston Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Wakefield | 4.0 |
| Stuart Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2022 | Mar 2022 | granted Jul 2022 | Apr 2022 | Wakefield | 4.1 |
| DHL, Waindyke Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Wakefield | 4.2 |
| Ferrybridge MFE, Kirkhaw Lane Solar PV Equipmentrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Wakefield | 4.9 |
| Morrisons Supermarketrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Wakefield | 6.5 |
| Stranglands Lanebattery storage | battery storage | — | approved, not builtupdated Jul 2025 | Mar 2024 | granted May 2025 | Jul 2025 | Wakefield | 7.0 |
| Sturton Grange, Ridge Roadrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Leeds | 7.7 |
| Vehicle Testing Station, Patrick Greenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Wakefield | 8.2 |
| Light Valley Solar, Selby Road -Battery Energy Storagebattery storage | battery storage | — | application submittedupdated Jun 2026 | Mar 2026 | — | Jun 2026 | North Yorkshire | 8.9 |
| Manheim Car Auctions, Rothwellrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Sep 2025 | granted Oct 2025 | Nov 2025 | Leeds | 9.3 |
| Pinderfields General Hospital, Aberford Roadrooftop solar | rooftop solar | — | approved, not builtupdated Dec 2025 | Sep 2025 | granted Oct 2025 | Dec 2025 | Wakefield | 9.9 |
Distance from the average position of the WF10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 3 | 3 | 3 | 1 | 654 |
| Rooftop solar | 16 | 1 | 15 | 0 | 0 | 11.9 |
| Wind farm | 3 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 17 | 4 | 8 | 2 | 0 | 1,105 |
MW in pipeline: pending, approved and under-construction capacity.
How Wakefield decides solar, wind and battery applications
| Applications | Wakefield | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 7 (16%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 9.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WF10, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.