Energy Projects Near You

Rawfield Lane (200 MW battery storage)

Rawfield Lane is a 200 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 August 2025, not yet built; the record was last updated on 11 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
11 September 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
4 October 2024Application submitted
21 August 2025Planning permission granted
21 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
11 September 2025
Operator or applicant
Harmony Energy Limited
Planning authority
North Yorkshire
Planning application reference
ZG2024/1317/FULM
Address (REPD)
East Of Rawfield Lane Fairburn
Council area (by location)
North Yorkshire
Time to decision
46 weeks
Name in REPD
Rawfield Lane - Battery Energy Storage System
REPD reference
17502

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monk Fryston Battery Storagebattery storage320under construction1.1
Monk Fryston Battery Storagebattery storage57under construction1.3
Kirkhaw Lane Battery Storage Energybattery storage150operational3.0
Kirkhaw Lanebattery storage20operational3.3
Kirkhaw Lanebattery storage100abandoned3.3
Solar Farm at Light Valley Solar Sitessolar farm500application submitted3.8
Hillam Grange, Austfield Lane Solar Farmsolar farm49.9approved, not built3.9
Newton Lane, Ledstonbattery storage25approved, not built4.8
Knottingley Asolar farm5operational5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7476, -1.2809).