Hillam Grange, Austfield Lane Solar Farm (49.9 MW)

Hillam Grange, Austfield Lane Solar Farm is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 December 2025, not yet built; the record was last updated on 26 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
26 January 2026record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
19 December 2023Application submitted
25 March 2025Refused by the planning authority
16 July 2025Appeal lodged
19 December 2025Planning permission granted
19 December 2025Appeal allowed
19 December 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
26 January 2026
Operator or applicant
Noventum Power Limited
Planning authority
North Yorkshire
Planning application reference
ZG2023/1271/FULM
Appeal reference
AP/2025/0037/REF
Site area
62.7 ha
Address (REPD)
Hillam Grange Austfield Lane Hillam
Council area (by location)
North Yorkshire
Time to decision
104 weeks
Name in REPD
Hillam Grange, Austfield Lane - Solar Farm
REPD reference
14040

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Light Valley Solar Sitessolar farm500application submitted0.4
Monk Fryston Battery Storagebattery storage57under construction2.7
Monk Fryston Battery Storagebattery storage320under construction2.9
Wood Lanewind farm32.2application withdrawn3.3
Rawfield Lanebattery storage200approved, not built3.9
Kingspan Insulation Solar Installationrooftop solar5operational4.1
Land at Ash Row Farmsolar farm5operational4.4
Kirkhaw Lane Battery Storage Energybattery storage150operational5.3
Weeland Road, Kellingley Solar Farmsolar farm10application submitted5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7575, -1.2236).