Kirkhaw Lane Battery Storage Energy (150 MW)

Kirkhaw Lane Battery Storage Energy is a 150 MW battery storage project in Wakefield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2026; the record was last updated on 31 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWbattery storage
operationalstatus in REPD
31 March 2026record last updated
Wakefieldcouncil area

Planning timeline

DateStage
11 November 2021Application submitted
6 June 2023Planning permission granted
23 March 2026Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
150 MW
Status (REPD)
operational
Record last updated
31 March 2026
Operator or applicant
SSE Enterprise Contracting
Planning authority
Wakefield
Planning application reference
21/02758/CPL
Address (REPD)
Ferrybridge Power Station, Kirkhaw Lane, Knottingley
Council area (by location)
Wakefield
Time to decision
82 weeks
Name in REPD
Kirkhaw Lane - Battery Storage Energy
REPD reference
10022

Earlier applications for this site

ApplicationMWSubmittedOutcome
Kirkhaw Lane Battery Storage Energy 21/02055/CPL10010 August 2021replaced by a revised application

Who decides

ApplicationsWakefieldUK
Decided applications (solar, wind, battery)4510,236
Refused7 (16%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused1 of 816%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kirkhaw Lanebattery storage20operational0.3
Kirkhaw Lanebattery storage100abandoned0.4
Rawfield Lanebattery storage200approved, not built3.0
Knottingley Asolar farm5operational3.0
Monk Fryston Battery Storagebattery storage320under construction3.7
Monk Fryston Battery Storagebattery storage57under construction3.8
Pontefract Wind Farmwind farm12refused on appeal4.4
Stocking Lane Battery Energy Facilitybattery storage200application submitted4.7
Leys Lanesolar farm49.9application submitted4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7211, -1.276).