Leys Lane (49.9 MW solar farm)

Leys Lane is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 3 June 2025, no decision recorded; the record was last updated on 24 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
24 October 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
3 June 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
24 October 2025
Operator or applicant
Farm Energy Company
Planning authority
North Yorkshire
Planning application reference
ZG2025/0100/EIA
Site area
41.8 ha
Address (REPD)
E/O Leys Lane, Knottingley
Council area (by location)
North Yorkshire
Name in REPD
Leys Lane - Solar Panels
REPD reference
19160

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Knottingley Asolar farm5operational2.0
Sudforth Lane (Kellingley Solar Farm)solar farm5operational2.8
Stocking Lane Battery Energy Facilitybattery storage200application submitted3.0
Darrington Quarrywind farm16application withdrawn3.0
Weeland Road, Kellingley Solar Farmsolar farm10application submitted3.2
Kirkhaw Lanebattery storage100abandoned4.5
Kirkhaw Lanebattery storage20operational4.6
Corner Of Weeland Road, Lunn Lanebattery storage200approved, not built4.7
Kirkhaw Lane Battery Storage Energybattery storage150operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.6861, -1.2328).