Sudforth Lane (Kellingley Solar Farm) (5 MW)

Sudforth Lane (Kellingley Solar Farm) is a 5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2017; the record was last updated on 31 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 October 2017record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
22 April 2015Application submitted
7 August 2015Planning permission granted
15 January 2017Construction started
30 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 October 2017
Operator or applicant
First Renewable Developments/ Harworth Group
Planning authority
North Yorkshire
Planning application reference
2015/0415/FUL
Site area
11.4 ha
Address (REPD)
Sudforth Lane, Beal, Goole, Humberside
Council area (by location)
North Yorkshire
Time to decision
15 weeks
REPD reference
5559

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Weeland Road, Kellingley Solar Farmsolar farm10application submitted0.8
Stocking Lane Battery Energy Facilitybattery storage200application submitted0.8
Corner Of Weeland Road, Lunn Lanebattery storage200approved, not built2.0
Knottingley Asolar farm5operational2.7
Leys Lanesolar farm49.9application submitted2.8
Eggborough Battery Energy Storage Systembattery storage550approved, not built3.1
Wood Lanewind farm32.2application withdrawn4.0
Springfield Farm, Hensallbattery storage240approved, not built4.7
Springfield Farm, Weeland Roadbattery storage240approved, not built4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7028, -1.2009).