Hook Moor (10.3 MW wind farm)

Hook Moor is a 10.3 MW wind farm project in Leeds, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2016; the record was last updated on 26 February 2016.

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.3 MWwind farm
operationalstatus in REPD
26 February 2016record last updated
Leedscouncil area

Planning timeline

DateStage
26 February 2008Application submitted
4 August 2009Refused by the planning authority
9 December 2011Planning permission granted
9 December 2011Appeal allowed
11 March 2015Construction started
15 January 2016Operational

Project details

Technology
wind farm
Capacity
10.3 MW
Status (REPD)
operational
Record last updated
26 February 2016
Operator or applicant
Banks Renewables
Planning authority
Leeds
Planning application reference
08/01118/FU
Appeal reference
APP/N4720/A/10/2121279
Turbines
5 (OnPath Energy; REPD: 3)
Turbine height
125 m
Address (REPD)
Land at Hook Moor , Micklefield , Leeds
Council area (by location)
Leeds
Time to decision
197 weeks
REPD reference
4658

Hook Moor near Micklefield, east of Leeds, reached consent through a refusal: Leeds council rejected the application, and the project only received planning permission after an appeal. It is a Banks Renewables wind farm with five turbines (three in the REPD), each 125 m tall, 10.3 MW in total.

Refusal, appeal, construction

The application was submitted on 26 February 2008, and the council refused it on 4 August 2009. The appeal was allowed, and consent was granted on 9 December 2011: 197 weeks from application. For Leeds this is rare: out of 68 decided applications for solar, wind and batteries, 7 were refused (10%, against 19% for UK councils), with a median of 7.3 weeks. Construction began on 11 March 2015, and power first flowed on 15 January 2016.

No other wind farms nearby

Among large projects within 10 km there are no wind ones: the solar farm Hayton House Farm at 49.9 MW is awaiting a decision, and the battery storage Monk Fryston at 320 MW is under construction. More on the pages for Leeds and LS25. Record last updated on 26 February 2016, REPD extract for July 2026.

Who decides

ApplicationsLeedsUK
Decided applications (solar, wind, battery)6810,236
Refused7 (10%)19%
Solar refused2 of 5812%
Onshore wind refused1 of 145%
Battery storage refused4 of 916%
Median time from submission to decision7.3 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leeds, West Yorkshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hayton House Farm Solar Farmsolar farm49.9application submitted3.5
Barnsdale Road Solar Parksolar farm40under construction6.4
Land off Paradise Farmsolar farm5refused6.5
Warren Lane, Bramhambattery storage35approved, not built6.9
Newton Lane, Ledstonbattery storage25approved, not built7.3
Kingspan Insulation Solar Installationrooftop solar5operational7.5
Monk Fryston Battery Storagebattery storage320under construction7.9
Monk Fryston Battery Storagebattery storage57under construction7.9
Land at Ash Row Farmsolar farm5operational7.9