Warren Lane, Bramham (35 MW battery storage)

Warren Lane, Bramham is a 35 MW battery storage project in Leeds, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
Leedscouncil area

Planning timeline

DateStage
19 September 2023Application submitted
21 June 2024Refused by the planning authority
15 July 2025Planning permission granted
15 July 2025Appeal allowed
15 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Harmony Energy Limited
Planning authority
Leeds
Planning application reference
23/04572/FU
Address (REPD)
Warren Lane, Bramham, Tadcaster
Council area (by location)
Leeds
Time to decision
95 weeks
Name in REPD
Warren Lane, Bramham - Battery Energy Storage
REPD reference
14954

Who decides

ApplicationsLeedsUK
Decided applications (solar, wind, battery)6810,236
Refused7 (10%)19%
Solar refused2 of 5812%
Onshore wind refused1 of 145%
Battery storage refused4 of 916%
Median time from submission to decision7.3 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leeds, West Yorkshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Land off Paradise Farmsolar farm5refused1.7
Hayton House Farm Solar Farmsolar farm49.9application submitted3.6
Hook Moorwind farm10.3operational6.9
Moto Wetherby Motorway Service Area, Deighton Gates Roundabout Solar Farmsolar farm7approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8739, -1.3228).