Energy Projects Near You

Solar, wind and battery projects near Wetherby (LS22)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LS22 (Leeds): 8 approved but not yet running. The largest live scheme is Warren Lane, Bramham (35 MW battery storage, approved on 15 July 2025, not yet built), 8.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
0awaiting a decision
8approved, not running
0operational

Projects within 10 km of LS22

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Moto Wetherby Motorway Service Area, Deighton Gates Roundabout Solar Farmsolar farmsolar farm7approved, not builtupdated Aug 2024Nov 2023granted Aug 2024Aug 2024North Yorkshire2.4
Land off Paradise Farmsolar farmsolar farm5refusedupdated Jan 2016May 2015refused Dec 2015Jan 2016Leeds7.6
Warren Lane, Bramhambattery storagebattery storage35approved, not builtupdated Jul 2025Sep 2023granted Jul 2025Jul 2025Leeds8.0
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Harrogate Roadsolar farmsolar farm0.2approved, not built may be out of dateupdated Aug 2022Jul 2022granted Sep 2022Aug 2022North Yorkshire2.4
Harrogate South Waste Water Treatment Works - Ground Mounted Solar Arraysolar farmsolar farm0.4approved, not builtupdated Aug 2023Jun 2023granted Jun 2023Aug 2023North Yorkshire4.9
British Library, Thorp Arch Estate -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Leeds5.1
The British Library Building, Boston Spa Solar PV Equipmentrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Leeds5.1
J Revis & Sons, South Field Lanerooftop solarrooftop solar0.5approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023North Yorkshire6.5
Flaxby Moor Works, Flaxbyrooftop solarrooftop solar0.2approved, not builtupdated Sep 2021Jul 2021granted Sep 2021Sep 2021North Yorkshire8.1

Distance from the average position of the LS22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm403017.5
Rooftop solar404001.3
Battery storage1010035

MW in pipeline: pending, approved and under-construction capacity.

How Leeds decides solar, wind and battery applications

ApplicationsLeedsUK
Decided applications (solar, wind, battery)6810,236
Refused7 (10%)19%
Solar refused2 of 5812%
Onshore wind refused1 of 145%
Battery storage refused4 of 916%
Median time from submission to decision7.3 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leeds, West Yorkshire.

All projects in Leeds

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LS22, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.