Hessay Solar Farm (40 MW)

Hessay Solar Farm is a 40 MW solar farm project in York, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 March 2024, not yet built; the record was last updated on 14 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
14 March 2024record last updated
Yorkcouncil area

Planning timeline

DateStage
6 April 2023Application submitted
11 March 2024Planning permission granted
11 March 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
14 March 2024
Operator or applicant
Solar2 Limited
Planning authority
York
Planning application reference
23/00626/FULM
Site area
61.3 ha
Address (REPD)
The North And South Of Low Moor Lane Hessay York
Council area (by location)
York
Time to decision
49 weeks
Contracts for Difference
AR6
REPD reference
11974

Who decides

ApplicationsYorkUK
Decided applications (solar, wind, battery)3810,236
Refused4 (11%)19%
Solar refused2 of 3112%
Battery storage refused2 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Harewood Whin, Tinker Lane Solar Farmsolar farm28approved, not built2.0
Poppleton Solar Farmsolar farm32.6approved, not built2.7
Green Lane, Moor Monkton Solar Panels & Battery Energy Storage Systemsolar farm49.9application submitted3.5
Overton Grange, Overton Road Solar Farm Battery Energy Storagesolar farm49.9application submitted4.0
Sutton-on-the-Forest, Brownmoor Lane Solar Parksolar farm49.9application submitted8.4
Sutton-on-the-Forest, Brownmoor Lane -BESSbattery storage10application submitted8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9736, -1.1975).