Energy Projects Near You

Land South of Highfield House (5 MW solar farm)

Land South of Highfield House is a 5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2016; the record was last updated on 24 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
24 August 2016record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
20 February 2015Application submitted
29 June 2015Planning permission granted
14 January 2016Construction started
15 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
24 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
North Yorkshire
Planning application reference
15/00318/FUL
Site area
11.1 ha
Address (REPD)
Land South East Of Highfield House, Husthwaite, York, North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
18 weeks
REPD reference
5033

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Boscar Grange Farmbattery storage27operational0.5
York Solar Farmsolar farm34.7operational0.5
Os Field, Husthwaitesolar farm49.9approved, not built1.3
Boscar Layby, Raskelfsolar farm30application submitted2.0
Pilmoor Solar Farmsolar farm50approved, not built4.0
Cold Harbour Farmsolar farm5operational5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1481, -1.2324).