Station Lane, South Stainley (10 MW solar farm)

Station Lane, South Stainley is a 10 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 April 2024, not yet built; the record was last updated on 3 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
3 May 2024record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
28 November 2022Application submitted
17 April 2024Planning permission granted
17 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
3 May 2024
Operator or applicant
Boultbee Brooks Renewable Energy
Planning authority
North Yorkshire
Planning application reference
22/04423/FULMAJ
Site area
19.3 ha
Address (REPD)
North Of Burton Top Farm Station Lane South Stainley
Council area (by location)
North Yorkshire
Time to decision
72 weeks
Contracts for Difference
AR6
REPD reference
9102

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wormald Greenbattery storage33operational1.5
Cayton Solar farmsolar farm49.9approved, not built1.6
Wormald Green Solar Farmsolar farm43approved, not built2.1
Low Moor Lane, Scottonbattery storage200application submitted4.0
Jenny Field Drivebattery storage5approved, not built6.8
New Oaks, Station Roadbattery storage50application submitted8.2
High Boar Wind Farmwind farm8refused9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0633, -1.5334).