Energy Projects Near You

Jenny Field Drive (5 MW battery storage)

Jenny Field Drive is a 5 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 January 2018, not yet built; the record was last updated on 11 October 2023. REPD also records that the planning permission expired on 19 January 2021, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
approved, not builtmay be out of datestatus in REPD
11 October 2023record last updated
North Yorkshirecouncil area

REPD also records that the planning permission expired on 19 January 2021, so the project may not go ahead in this form.

Planning timeline

DateStage
6 November 2017Application submitted
19 January 2018Planning permission granted
19 January 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
11 October 2023
Operator or applicant
Enstor Power
Planning authority
North Yorkshire
Planning application reference
17/04644/FUL
Address (REPD)
The Hydro, Jenny Field Drive, Harrogate,
Council area (by location)
North Yorkshire
Time to decision
11 weeks
REPD reference
7075

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Low Moor Lane, Scottonbattery storage200application submitted4.5
High Boar Wind Farmwind farm8refused4.6
Penny Pot Wind Farmwind farm21application withdrawn5.7
Knabs Ridge Windfarmwind farm16operational6.5
Station Lane, South Stainleysolar farm10approved, not built6.8
Kellingley Farm, Stocking Lanebattery storage240application submitted7.0
Cayton Solar farmsolar farm49.9approved, not built7.3
Wormald Green Solar Farmsolar farm43approved, not built8.0
Wormald Greenbattery storage33operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0032, -1.5501).