Cayton Solar farm (49.9 MW)

Cayton Solar farm is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 January 2022, not yet built; the record was last updated on 18 August 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
18 August 2023record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
14 June 2019Application submitted
13 January 2022Planning permission granted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
18 August 2023
Operator or applicant
Elgin Energy
Planning authority
North Yorkshire
Planning application reference
19/02259/FULMAJ
Site area
85.0 ha
Address (REPD)
High Cayton, Water Lane To Cayton, South Stainley, Harrogate, North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
135 weeks
Contracts for Difference
AR4
REPD reference
6561

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Station Lane, South Stainleysolar farm10approved, not built1.6
Wormald Greenbattery storage33operational2.3
Wormald Green Solar Farmsolar farm43approved, not built3.5
Low Moor Lane, Scottonbattery storage200application submitted5.4
Jenny Field Drivebattery storage5approved, not built7.3
New Oaks, Station Roadbattery storage50application submitted8.3
High Boar Wind Farmwind farm8refused9.0
Penny Pot Wind Farmwind farm21application withdrawn9.8
Knabs Ridge Windfarmwind farm16operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0683, -1.556).