Energy Projects Near You

Juniper Farm, Main Street (10 MW battery storage)

Juniper Farm, Main Street is a 10 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 July 2025, no decision recorded; the record was last updated on 29 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
application submittedstatus in REPD
29 August 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
22 July 2025Application submitted

Project details

Technology
battery storage (co-located with re)
Capacity
10 MW
Status (REPD)
application submitted
Record last updated
29 August 2025
Operator or applicant
ABEI Energy Group
Planning authority
North Yorkshire
Planning application reference
25/02219/FULMAJ
Address (REPD)
Juniper Farm, N/O Main Street And E/O Woodgate Lane, Weeton, Leeds
Council area (by location)
North Yorkshire
Name in REPD
Juniper Farm, Main Street - BESS
REPD reference
16763

Recorded together with Juniper Farm, Main Street Solar Farm (18.8 MW solar farm, application submitted).

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kellingley Farm, Stocking Lanebattery storage240application submitted7.0
High Boar Wind Farmwind farm8refused9.4
Penny Pot Wind Farmwind farm21application withdrawn9.7
Jenny Field Drivebattery storage5approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9154, -1.5751).