Energy Projects Near You

East Heslerton Wind Farm (25 MW)

East Heslerton Wind Farm is a 25 MW wind farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 28 May 2014; the record was last updated on 30 July 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWwind farm
refused on appealstatus in REPD
30 July 2014record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
18 March 2011Application submitted
16 May 2013Refused by the planning authority
28 May 2014Appeal refused

Project details

Technology
wind farm
Capacity
25 MW
Status (REPD)
refused on appeal
Record last updated
30 July 2014
Operator or applicant
RWE npower
Planning authority
North Yorkshire
Planning application reference
11/00270/MFULE
Appeal reference
13/00015/REF
Turbines
10
Address (REPD)
Ling Hall Farm West Heslerton Malton North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
113 weeks
REPD reference
4162

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Third Energy UK Gas Limitedbattery storage100approved, not built5.1
Sherburnrooftop solar5operational5.7
Carr House Farm, East Heslerton Solar Farmsolar farm23.5approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1466, -0.5915).