East Heslerton Wind Farm (25 MW)
East Heslerton Wind Farm is a 25 MW wind farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 28 May 2014; the record was last updated on 30 July 2014.
25 MWwind farm
refused on appealstatus in REPD
30 July 2014record last updated
North Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 March 2011 | Application submitted |
| 16 May 2013 | Refused by the planning authority |
| 28 May 2014 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 25 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 30 July 2014
- Operator or applicant
- RWE npower
- Planning authority
- North Yorkshire
- Planning application reference
- 11/00270/MFULE
- Appeal reference
- 13/00015/REF
- Turbines
- 10
- Address (REPD)
- Ling Hall Farm West Heslerton Malton North Yorkshire
- Council area (by location)
- North Yorkshire
- Time to decision
- 113 weeks
- REPD reference
- 4162
Who decides
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Third Energy UK Gas Limited | battery storage | 100 | approved, not built | 5.1 |
| Sherburn | rooftop solar | 5 | operational | 5.7 |
| Carr House Farm, East Heslerton Solar Farm | solar farm | 23.5 | approved, not built | 6.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1466, -0.5915).