Sherburn (5 MW rooftop solar)

Sherburn is a 5 MW rooftop solar project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 January 2016; the record was last updated on 3 November 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWrooftop solar
operationalstatus in REPD
3 November 2017record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
31 January 2014Application submitted
20 January 2016Operational
30 November 2016Construction started

Project details

Technology
rooftop solar
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 November 2017
Operator or applicant
Kingspan
Planning authority
North Yorkshire
Planning application reference
14/00132/MFUL
Address (REPD)
Widespan Works, Sherburn, Malton
Council area (by location)
North Yorkshire
REPD reference
6485

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carr House Farm, East Heslerton Solar Farmsolar farm23.5approved, not built3.0
East Heslerton Wind Farmwind farm25refused on appeal5.7
Third Energy UK Gas Limitedbattery storage100approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1793, -0.525).