Energy Projects Near You

Barugh Farm (5 MW solar farm)

Barugh Farm is a 5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2016; the record was last updated on 19 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
19 July 2017record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
1 November 2014Application submitted
26 January 2015Planning permission granted
1 December 2015Construction started
15 January 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
19 July 2017
Operator or applicant
HB & CH Barker Ltd
Planning authority
North Yorkshire
Planning application reference
14/04525/FULMAJ
Site area
5.8 ha
Address (REPD)
Barugh Farm, Hutton Conyers, Ripon
Council area (by location)
North Yorkshire
Time to decision
12 weeks
REPD reference
1838

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Oaks, Station Roadbattery storage50application submitted4.5
Land North of Sandhutton Lanesolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1751, -1.4955).