Energy Projects Near You

Land North of Sandhutton Lane (5 MW solar farm)

Land North of Sandhutton Lane is a 5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 December 2017record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
25 May 2015Application submitted
25 September 2015Planning permission granted
12 December 2016Construction started
15 February 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Greencoat Capital
Planning authority
North Yorkshire
Planning application reference
15/01074/FUL
Site area
18.0 ha
Address (REPD)
Land North Of, Sandhutton Lane, Carlton Miniott, Thirsk
Council area (by location)
North Yorkshire
Time to decision
18 weeks
REPD reference
5297

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cold Harbour Farmsolar farm5operational9.2
Barugh Farmsolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.237, -1.3985).