Energy Projects Near You

Brightenber Hill (7.5 MW wind farm)

Brightenber Hill is a 7.5 MW wind farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 February 2016; the record was last updated on 3 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
refused on appealstatus in REPD
3 March 2016record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
17 April 2012Application submitted
5 September 2012Refused by the planning authority
16 December 2014Appeal lodged
10 February 2016Appeal refused

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
refused on appeal
Record last updated
3 March 2016
Operator or applicant
Energiekontor UK
Planning authority
North Yorkshire
Planning application reference
05/2012/12568
Appeal reference
APP/C2708/A/12/2186488
Turbines
3
Address (REPD)
Land adjacent to Brightenber Hill near Stainton Hall, Gargrave, Skopton
Council area (by location)
North Yorkshire
Time to decision
20 weeks
REPD reference
4229

Earlier applications for this site

ApplicationMWSubmittedOutcome
Brightenber Hill 05/2008/888512.521 July 2008refused 18 February 2009

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land of coal pit lanesolar farm5operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9708, -2.1739).