Energy Projects Near You

Solar, wind and battery projects near Bedale (DL8)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DL8 (North Yorkshire): 3 approved but not yet running. The largest live scheme is AD Calvert Architectural, Stone Yard - Redevelopment Master Plan (0.5 MW solar farm, approved on 13 February 2024, not yet built), 4.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
3approved, not running
0operational

Projects within 10 km of DL8

Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fire Station, High Streetrooftop solarrooftop solar—approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026North Yorkshire3.7
AD Calvert Architectural, Stone Yard - Redevelopment Master Plansolar farmsolar farm0.5approved, not builtupdated Feb 2024Apr 2023granted Feb 2024Feb 2024North Yorkshire4.2
Babcock Land Defence Limited, Dsg Leyburn Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2024Jul 2024granted Sep 2024Dec 2024North Yorkshire9.5

Distance from the average position of the DL8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.5
Rooftop solar202000.3

MW in pipeline: pending, approved and under-construction capacity.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.