Energy Projects Near You

Solar, wind and battery projects near Northallerton (DL6)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DL6 (North Yorkshire): 3 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Mowbray Battery Energy Storage Station (1,000 MW battery storage, application submitted on 19 December 2024, no decision recorded), 7.9 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 36.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
3awaiting a decision
2approved, not running
1operational

Projects within 10 km of DL6

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bullamoorwind farmwind farm8permission expiredupdated Sep 2020Dec 2008granted Dec 2010Sep 2020North Yorkshire0.2
Northallertonsolar farmsolar farm28abandonedupdated Jun 2018Jun 2015granted Oct 2015Jun 2018North Yorkshire3.9
Solar Farm at N/O Black Bridge Danby Wiskesolar farmsolar farm19application submittedupdated Jul 2025May 2025—Jul 2025North Yorkshire7.3
Mowbray Battery Energy Storage Stationbattery storagebattery storage1,000application submittedupdated Feb 2025Dec 2024—Feb 2025North Yorkshire7.9
North East of Ainderby Steeplesolar farmsolar farm5.9operationalupdated Dec 2017Mar 2014granted Dec 2014Dec 2017North Yorkshire8.1
Ainderby Steeplesolarsolar1.5refusedupdated Dec 2014Feb 2014refused Nov 2014Dec 2014North Yorkshire8.1
East Cowton Solar Farmsolar farmsolar farm30.8application submittedupdated Aug 2025Jul 2025—Aug 2025North Yorkshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Darlington Roadrooftop solarrooftop solar0.4application withdrawnupdated Nov 2022Sep 2022—Nov 2022North Yorkshire3.7
Friarage Hospitalrooftop solarrooftop solar0.4approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025North Yorkshire4.0
Lark Hall Farm, Romanby - Ground Mounted Solar Panelssolar farmsolar farm0.3approved, not built may be out of dateupdated Aug 2022Jul 2022granted Mar 2023Aug 2022North Yorkshire6.6

Distance from the average position of the DL6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5211050.1
Rooftop solar201000.4
Solar100010
Wind farm100000
Battery storage110001,000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201536.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DL6, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.