Energy Projects Near You

Solar, wind and battery projects near Middlesbrough (TS9)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS9 (North Yorkshire): 3 approved but not yet running, 3 operational. The largest live scheme is Rainbow Leisure Centre, Dalby Way (0.3 MW rooftop solar, approved on 19 December 2024, not yet built), 7.3 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 20.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
3approved, not running
3operational

Projects within 10 km of TS9

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Seamer Windfarm - Stockton on Teeswind farmwind farm6operationalupdated Nov 2012Mar 2009granted Aug 2009Nov 2012North Yorkshire6.8
Seamer Wind Farm - Hambletonwind farmwind farm4operationalupdated Nov 2012Mar 2009granted Sep 2009Nov 2012Stockton-on-Tees7.1
Land at Woodhouse Farmsolar farmsolar farm5operationalupdated Aug 2016May 2015granted Nov 2015Aug 2016Redcar and Cleveland9.6
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rainbow Leisure Centre, Dalby Wayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Middlesbrough7.3
Stainton Way - Micro Energy storagebattery storagebattery storage0.2application withdrawnupdated May 2025Sep 2024—May 2025Middlesbrough7.5
Viewley Hill Academy, Andover Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Sep 2023granted Nov 2023Jan 2024Middlesbrough7.9
Marton Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Dec 2025Aug 2025refused Oct 2025Dec 2025Middlesbrough9.0
Sainsburys, Morgan Driverooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026Redcar and Cleveland10.0

Distance from the average position of the TS9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100100
Rooftop solar303000.7
Wind farm200200
Battery storage200010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201520.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.