Energy Projects Near You

Solar, wind and battery projects near Middlesbrough (TS8)

39 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS8 (Middlesbrough): 2 are waiting for a planning decision, 24 approved but not yet running, 5 operational. The largest live scheme is Old Hall Farm, Lackenby (244 MW battery storage, application submitted on 13 August 2025, no decision recorded), 8.3 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 16.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39projects within 10 km
2awaiting a decision
24approved, not running
5operational

Projects within 10 km of TS8

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Seamer Wind Farm - Hambletonwind farmwind farm4operationalupdated Nov 2012Mar 2009granted Sep 2009Nov 2012Stockton-on-Tees3.5
Seamer Windfarm - Stockton on Teeswind farmwind farm6operationalupdated Nov 2012Mar 2009granted Aug 2009Nov 2012North Yorkshire3.5
Bowesfield Flexible Energy Parkbattery storagebattery storage8approved, not built may be out of dateupdated Oct 2021Jan 2021granted Oct 2021Oct 2021Stockton-on-Tees5.8
Riverside Stadiumwind turbinewind turbine1.5permission expiredupdated Aug 2016May 2008granted Jul 2008Aug 2016Middlesbrough6.3
Lambs Hillwind farmwind farm8operationalupdated Feb 2017Oct 2010granted Dec 2011Feb 2017Stockton-on-Tees6.6
The Brick Bankbattery storagebattery storage7permission expiredupdated Oct 2023Jul 2018granted Jan 2019Oct 2023Stockton-on-Tees6.7
Wilton Engineering Services, Port Clarence Offshore Baserooftop solarrooftop solar1.2approved, not builtupdated Jan 2026Sep 2025granted Sep 2025Jan 2026Stockton-on-Tees7.2
Norton Bottomssolar farmsolar farm5application withdrawnupdated Mar 2017Feb 2016—Mar 2017Stockton-on-Tees7.8
Eaglescliffe Solar Farmsolar farmsolar farm5operationalupdated May 2017Sep 2015granted Dec 2015May 2017Stockton-on-Tees8.2
Old Hall Farm, Lackenbybattery storagebattery storage244application submittedupdated Sep 2025Aug 2025—Sep 2025Redcar and Cleveland8.3
Lackenbybattery storagebattery storage49.9permission expiredupdated Aug 2020Jul 2019granted Oct 2019Aug 2020Redcar and Cleveland8.5
Wilton International, Greystones Road - Phase 1battery storagebattery storage150approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Redcar and Cleveland8.7
Greystones Road, Grangetownbattery storagebattery storage60approved, not builtupdated Nov 2021Oct 2021granted Dec 2021Nov 2021Redcar and Cleveland8.7
Belasis Avenuebattery storagebattery storage75approved, not builtupdated Aug 2025Aug 2023granted Apr 2024Aug 2025Stockton-on-Tees8.9
Smaller schemes under 1 MW, mostly rooftop solar (25)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Viewley Hill Academy, Andover Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Sep 2023granted Nov 2023Jan 2024Middlesbrough0.3
Stainton Way - Micro Energy storagebattery storagebattery storage0.2application withdrawnupdated May 2025Sep 2024—May 2025Middlesbrough0.7
Rainbow Leisure Centre, Dalby Wayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Middlesbrough1.1
Marton Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Dec 2025Aug 2025refused Oct 2025Dec 2025Middlesbrough2.6
The Vale - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Jun 2025Sep 2024refused May 2025Jun 2025Middlesbrough3.5
The North West & South East Sides Of The A19 Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Dec 2025Sep 2024granted Nov 2025Dec 2025Middlesbrough4.2
Hollywood Bowl, Aintree Oval Solar Photovoltaics Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Middlesbrough5.0
Breckon Hill Primary School, Breckon Hill Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Middlesbrough5.4
Albert Road Rooftop Solar Panelsrooftop solarrooftop solar0.2operationalupdated Sep 2021Nov 2020granted Mar 2021Sep 2021Middlesbrough5.8
Cargo Fleet Lanerooftop solarrooftop solar0.2abandonedupdated Feb 2024Jun 2022—Feb 2024Middlesbrough5.8
Endeavour Houserooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Stockton-on-Tees6.0
David Lloyd Club, Tees Barrage Wayrooftop solarrooftop solar0.5approved, not builtupdated Nov 2023Jul 2023granted Nov 2023Nov 2023Stockton-on-Tees6.2
Armadillo Self Storage, North Tees Industrial Estaterooftop solarrooftop solar0.1approved, not builtupdated Jun 2025May 2025granted May 2025Jun 2025Stockton-on-Tees6.3
Zetland Multi Storey Car Park, Station Streetrooftop solarrooftop solar—approved, not builtupdated Nov 2022Aug 2022granted Sep 2022Nov 2022Middlesbrough6.4
Riverside Park Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022Middlesbrough6.5
Dunedin House,Columbia Driverooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Stockton-on-Tees6.8
Motorpoint, Yarm Road Solar photovoltaics panelsrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Jul 2022May 2022Stockton-on-Tees7.1
Bulkhaul, Brignell Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2025Feb 2025granted Mar 2025May 2025Middlesbrough7.2
Riverside Park Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Jun 2025Sep 2024granted May 2025Jun 2025Middlesbrough7.2
Roman Terrace Solar Farmsolar farmsolar farm—approved, not builtupdated Nov 2025Jan 2025granted Jul 2025Nov 2025Redcar and Cleveland7.3
Teesside Recycling Centre, Puddlers Roadrooftop solarrooftop solar—approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Redcar and Cleveland7.7
CSG Limited, Holden Closerooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Redcar and Cleveland8.0
Huntsman Drive, Seal Sandsrooftop solarrooftop solar0.4application submittedMay 2026——Stockton-on-Tees8.7
Sainsburys Supermarket, Barlborough Avenuerooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Stockton-on-Tees8.9
Fairfield Primary School, Glenfield Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Stockton-on-Tees9.6

Distance from the average position of the TS8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm301100
Rooftop solar20117105.3
Wind farm300300
Wind turbine100000
Battery storage121602537

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201516.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Middlesbrough decides solar, wind and battery applications

ApplicationsMiddlesbroughUK
Decided applications (solar, wind, battery)1410,236
Refused4 (29%)19%
Solar refused0 of 812%
Onshore wind refused0 of 145%
Battery storage refused4 of 516%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

All projects in Middlesbrough

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS8, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.